    If 40 men can complete a work in 10 days working 10 hours a day, then find the number of men is required to finish the work in 5 days if they work 10 hours in a day.

    A)  100 men

    B)  60 men

    C)  150 men

    D)  80 men

    E)  None of these

    Correct Answer: D

    Solution :

       