8th Class Mathematics Related to Competitive Exam Question Bank Arithmetic

  • question_answer
    P and Q can do a job in 25 days and 30 days respectively. They work together for 5 days and then p leaves. Q will finish the rest of work in how many days?

    A) 19 days            

    B) 25 days

    C) 35 days                 

    D) 30 days

    Correct Answer: A

    Solution :

    \[{{I}_{2}}=\frac{PTR}{100}\] \[=\frac{1800\times 2\times 12}{100}\] \[=\frac{1200\times 3\times 18}{100}\]'s 5 days work \[=Rs.432\] Remaining work \[=Rs.648\] Q can finish the work in 30 days. Q can finish the \[{{I}_{1}}:{{I}_{2}}=432:648=2:3.\] work in \[\frac{19}{30}\times 30=19\]days.        