    The essential condition for the decompression of an activity is:

    A) The project time should change due to de- compression

    B) After decompression the time of an activity invariably exceeds its normal time

    C) An activity could be decompressed to the maximum extent of its normal time

    D) None of the above.

    Correct Answer: C