    Consider the following steps:
    1. Method time measurement
    2. Work sampling
    3. Work factor system.
    PMTS (predetermined motion time systems) in work study would include:

    A) 1, 2 and 3                     

    B) 1, 3 and 4

    C) 1, 2 and 4                     

    D) 1, 2 and 3

    Correct Answer: D