Railways NTPC (Technical Ability) Metrology and Inspection Question Bank Metrology and Inspection

  • question_answer
    Match List-I with List-II and select the correct answer using the codes given below the lists:
    List-I List-II
    A. Control charts for variables   1. Binomial distribution
    B. Control chart non-conformities 2. Beta for number of distribution
    C. Control chart for fraction rejected             3. Normal distribution
    D. Activity time distribution in PERT      4. Poisson distribution
    5. Exponential distribution
    Codes:

    A) A\[\to \]3, B\[\to \]4, C\[\to \]1, D\[\to \]5

    B) A\[\to \]5, B\[\to \]4, C\[\to \]3, D\[\to \]1

    C) A\[\to \]4, B\[\to \]3, C\[\to \]1, D\[\to \]2

    D) A\[\to \]3, B\[\to \]4, C\[\to \]1, D\[\to \]2

    Correct Answer: D