    Match List-I (Charts) with List-II (Details) and select the correct answer using the codes given below the lists:
    List-I List-II
    A. Multiple activity 1. Work factor chart system
    B. SIMO chart      2. Movement of material
    C. String diagram   3. Motion analysis
    D. MTM 4. Working an idle time of two or more men/machines
    Codes:

    A) A\[\to \]4, B\[\to \]3, C\[\to \]2, D\[\to \]1

    B) A\[\to \]3, B\[\to \]4, C\[\to \]2, D\[\to \]1

    C) A\[\to \]4, B\[\to \]3, C\[\to \]1, D\[\to \]2

    D) A\[\to \]3, B\[\to \]4, C\[\to \]1, D\[\to \]2

    Correct Answer: A