    12 men can complete a work in 30 days by working 9 hours a day. What is the number of men required to complete 10 times of this work in 24 days by working 5 hours a day?

    A) 230                 

    B)          170

    C) 310                 

    D)          270

    Correct Answer: D

    Solution :

        12 men can complete a work in 30 days by working 9 hours a day. \[\therefore \] 1 man can complete a work in 1 day by working \[(12\times 30\times 9)\] hours. Let the number of men required be x. Then x men can complete 10 times the work in 24 days by working 5 hours a day. \[\therefore \] 1 man can complete 1 work in 1 day by working \[\frac{x\times 24\times 5}{10}\] hours \[\therefore \,\,12\times 30\times 9=\frac{x\times 24\times 5}{10}\] \[\Rightarrow \,\,x=270\,\] men.