A) 4 hours
B) 6 hours
C) 7 hours
D) 9 hours
Correct Answer: B
Solution :
To complete the work in 18 days, 10 men work 6 hours a day To complete the work in 18 days, 1 man work (10 x 6) hours a day To complete the work in a day, 1 man will work \[(6\times 10\times 18)\] hours in a day (less days, less men, more hours) To complete the work in 1 day, 15 men will work \[\frac{(6\times 10\times 18)}{15}\] hours a day. \[\therefore \] To complete the work in 12 days, 15 men will work \[\left( \frac{6\times 10\times 18}{12\times 15} \right)\] hours a day. (more days, more men, less hours) = 6 hours a day.You need to login to perform this action.