Banking Sample Paper Bank of Baroda (PO) Sample Test Paper-1

  • question_answer
     A and B together can do a work in 8 days, B and C. together can do in 6 days while C and A together can do in 10 days. If they all work together, in how many days will they complete the work?

    A)  \[3\frac{1}{7}\]days                 

    B)  \[3\frac{3}{7}\,\,days\] 

    C)  \[5\frac{5}{47}\,\,days\]

    D)         \[4\frac{4}{9}\,\,days\]

    E)  \[3\frac{3}{17}\,\,days\]

    Correct Answer: C

    Solution :

                According to the question, LCM of 8, 6 and 10 - 120 \[\therefore \] (A + B) can. do \[\left( \frac{820}{8} \right)\] 15 units/day             Similarly, (B + C) can do \[\left( \frac{120}{6} \right)\]20 units/ day and (C + A) can do\[\frac{120}{10}\]= 12 units day Total efficiency = 15 + 20 + 12 \[\frac{47}{2}\] (A + B + C) together will complete the whole work in \[\frac{120\times 2}{47}=\frac{240}{47}=5\frac{5}{47}\] days Another method: (A + B) can do the work in \[\frac{1}{8}\] days (B + C) can do the work in\[\frac{1}{6}\] days (C + A) can do the work in \[\frac{1}{10}\] days 2(A + B+ C) together do the work \[=\frac{1}{8}+\frac{1}{6}+\frac{1}{10}=\frac{15+20+12}{120}=\frac{47}{120}\] (A + B + G) can do the whole work in \[\frac{120\times 2}{47}=5\frac{5}{47}\] days


You need to login to perform this action.
You will be redirected in 3 sec spinner