    A can do a piece of work in 30 days, B in 50 days and C in 40 days. If A is assisted by B on one day and by C on the next day alternately, work will be completed in

    A)  \[17\frac{32}{35}\] days                       

    B)        \[19\frac{2}{3}\] days  

    C)        \[16\frac{31}{37}\] days                       

    D)        \[18\frac{1}{3}\] days 

    Correct Answer: A

    Solution :

    \[(A+B)'s\] 1 day?s work \[=\frac{1}{30}+\frac{1}{20}=\frac{8}{150}\] \[\therefore \] \[(A+C)'s\] 1 days? work \[=\frac{1}{30}+\frac{1}{40}=\frac{7}{120}\] \[\therefore \] Work done in first 2 days \[=\frac{8}{150}+\frac{7}{120}=\frac{67}{600}\]             Work done is \[8\times 2=16\] days \[=\frac{67\times 8}{600}=\frac{67}{75}\] Work left \[=1-\frac{67}{75}=\frac{8}{75}\] On 17th day \[(A+B)\] will work and they will finish \[\frac{8}{150}\] work. \[\therefore \] Work left \[=\frac{8}{75}-\frac{8}{150}=\frac{8}{150}=\frac{4}{75}\] On 18th day (A + C) will work and they will finish it in \[\frac{120}{7}\times \frac{4}{75}=\frac{32}{35}\] So, whole work will be done in \[17\frac{32}{35}\] days.


You need to login to perform this action.
You will be redirected in 3 sec spinner