Railways Sample Paper RRB (Group D) Sample Test Paper-2

  • question_answer
    A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labors it was found that only 5/8th of the road had been constructed. To complete the work in stipulated time the number of extra labours required is:

    A)   12                  

    B)  10

    C)   18                  

    D)  16

    Correct Answer: D

    Solution :

    [d]  \[\begin{matrix}    Days & No.\,\,of\,\,Labourers & Work\,\,done  \\    12 & 20 & {5}/{8}\;  \\    4 & ? & 1-\frac{5}{8}=\frac{3}{8}  \\ \end{matrix}\] \[M_{1}^{{}}{{D}_{1.}}{{W}_{2}}={{M}_{2}}{{D}_{2}}{{W}_{1}}\] \[20\times 12\times \frac{3}{8}={{M}_{2}}\times 4\times \frac{5}{8}\Rightarrow {{M}_{2}}=\frac{20\times 12\times 3\times 8}{4\times 5\times 8}=36\] Hence,\[36-\,20=16\]more men needed to complete the remaining work in 4 days.