    Work done by A in one day is four times the work done by B in one day, while the work done by B in one day is one-third of the work done by C in one day. C alone can complete the work in 16 days. In how many days can all the three together complete the work?

    A)  12 days                       

    B)  10 days                       

    C)  8 days             

    D)  6 days             

    E)  Other than those given as options

    Correct Answer: D

    Solution :

    Ratio of efficiencies\[\begin{matrix}    {} & A & : & B & : & C  \\    = & \frac{4}{3} & : & \frac{1}{3} & : & 1  \\    = & 4 & : & 1 & : & 3  \\ \end{matrix}\] With 3 efficiency C takes 16 days \[\therefore \]With (4 + 1 + 3 =) 8 efficiency they will take \[\frac{16\times 3}{8}=6\] days