    A and B can do a piece of work in 8 days, B and C can do the same work in 12 days. If A, B and C can complete the same work in 6 days, un how many days can A and C complete the same work?

    A) 8 days  

    B) 10 days

    C) 12 days            

    D) 16 days

    Correct Answer: A

    Solution :

    Number of days taken by A and B to do the work = 8 Number of days taken by B and C to do the work = 12 A's and B's one day work \[=\frac{1}{8}\] B's and C's one day work \[=\frac{1}{12}\] Number of days taken by A's, B's and C's to do the work = 6 A's, B's and C's One day work \[=\frac{1}{6}\] B's one day work \[=\frac{1}{8}+\frac{1}{12}-\frac{1}{6}\]                          \[=\frac{1}{24}\] A's and C's one day work \[=\frac{1}{6}-\frac{1}{24}\]                         \[=\frac{3}{24}=\frac{1}{8}\] Hence, A and C can do the work in 8 days.           