Railways R.R.C. (Delhi) Solved Paper Held on 17-11-2013

  • question_answer
    A can doth of a piece of work in 3 days. Then the number of days required to complete rd of the work is?

    A) 12                                

    B) 9

    C) 15                                

    D) 18

    Correct Answer: A

    Solution :

    Let, x days required to complete, rd or the work.                         