A) \[x\ge 0,\ y\ge 0,\ 2x+3y\ge 70,\ 3x+2y\ge 75\]
B) \[x\ge 0,\ y\ge 0,\ 2x+3y\le 70,\ 3x+2y\ge 75\]
C) \[x\ge 0,\ y\ge 0,\ 2x+3y\ge 70,\ 3x+2y\le 75\]
D) \[x\ge 0,\ y\ge 0,\ 2x+3y\le 70,\ 3x+2y\le 75\]
Correct Answer: D
Solution :
| Type of items | Working time on machine | Man labour |
| Shirt (x) Pent (y) | 2 hours 3 hours | 3 hours 2 hours |
| Availability | 70 hours | 75 hours |