A) \[4\]
B) \[8\]
C) \[10\]
D) \[6\]
Correct Answer: B
Solution :
The job needs to be completed 2 days in advance, i.e., in \[8-2=6\]days. The number of men and the number of days are inversely proportional. \[\therefore \] \[6:x:\,\,:6:8\] \[\Rightarrow \] \[x=\frac{6\times 8}{6}=8\] \[\therefore \] 8 workers are needed to complete the job in 6 days.You need to login to perform this action.