List I (Work Study) | List II (Objective) | ||
A. | Motion study | 1. | Determining the standard time |
B. | Time study | 2. | Determining the amount and frequency of rest intervals |
C. | Method study | 3. | Eliminating unnecessary movements |
D. | Fatigue study | 4. | Finding out the one best way of doing the job |
A) A\[\to \]4, B\[\to \]3, C\[\to \]1, D\[\to \]2
B) A\[\to \]3, B\[\to \]4, C\[\to \]2, D\[\to \]1
C) A\[\to \]3, B\[\to \]1, C\[\to \]4, D\[\to \]2
D) A\[\to \]2, B\[\to \]4, C\[\to \]3, D\[\to \]1
Correct Answer: D