List-I (Type of Job) | List-II (Appropriate Method-study Technique) | ||
A. | Complete sequence of operations | 1. | Flow diagram |
B. | Factory layout: movement of materials | 2. | Flow process chart |
C. | Factory Layout: movement of workers | 3. | Multiple activity chart |
D. | Gang work | 4. | String diagram |
A) A\[\to \]4, B\[\to \]3, C\[\to \]2, D\[\to \]1
B) A\[\to \]2, B\[\to \]1, C\[\to \]4, D\[\to \]3
C) A\[\to \]4, B\[\to \]1, C\[\to \]2, D\[\to \]3
D) A\[\to \]2, B\[\to \]3, C\[\to \]4, D\[\to \]1
Correct Answer: B