Processing time | : | 16 minutes |
Rating of the worker | : | 120% |
Personal allowance | : | 0.6 minutes |
Basic fatigue allowance | : | 1.92 minutes |
Unavoidable delay allowance | : | 1.08 minutes |
A) 16 minutes
B) 17.92 minutes
C) 21.52 minutes
D) none of the above
Correct Answer: D