List-I | List-II | ||
A. | Moving Average | 1. | Assembly |
B. | Line Balancing | 2. | Purchase |
C. | Economic Batch Size | 3. | Forecasting |
D. | Johnson alogorithm | 4. | Sequencing |
A) A\[\to \]1, B\[\to \]3, C\[\to \]2, D\[\to \]4
B) A\[\to \]1, B\[\to \]3, C\[\to \]4, D\[\to \]2
C) A\[\to \]3, B\[\to \]1, C\[\to \]4, D\[\to \]2
D) A\[\to \]3, B\[\to \]1, C\[\to \]2, D\[\to \]4
Correct Answer: D