    Match List-I (Files in MRP) with List-II (Inputs required) and select the correct answer using the codes given below the lists:
    List-I (Files in MRP) List-II (Inputs required)
    A. Master Production Schedule   1. Scheduled Receipts
    B. Bills of Materials       2. Unit Costs and Discounts
    C. Inventory Records   3. Production Capacity
    D. 4. Product Structure
    Codes:

    A) A\[\to \]4, B\[\to \]1, C\[\to \]3

    B) A\[\to \]3, B\[\to \]4, C\[\to \]2

    C) A\[\to \]3, B\[\to \]4, C\[\to \]1

    D) A\[\to \]4, B\[\to \]3, C\[\to \]1

    Correct Answer: C