    The proper sequence of activities for material requirement planning are:

    A) Master production schedule, capacity planning, MRP and order release

    B) Order release, master production schedule, MRP and capacity planning

    C) Master production schedule, order release, capacity planning and MRP

    D) Capacity planning, master production schedule, MRP and order release.

    Correct Answer: D