List-I | List-II | ||
A. | Just-In-Time inventory and Procurement Techniques | 1. | Intermittent Production |
B. | Work-In-Process likely to be low compared to Output | 2. | Repetitive Production |
C. | Scheduling Typically Most Complex process | 3. | Continuous Production |
D. | Flexible Manufacturing cell | 4. | Job Production |
A) A\[\to \]2, B\[\to \]3, C\[\to \]4, D\[\to \]1
B) A\[\to \]3, B\[\to \]2, C\[\to \]1, D\[\to \]4
C) A\[\to \]2, B\[\to \]3, C\[\to \]1, D\[\to \]4
D) A\[\to \]3, B\[\to \]2, C\[\to \]4, D\[\to \]1
Correct Answer: A