    Which of the following are the objectives of scheduling?
    1. Reducing average waiting time of a batch
    2. To meet the deadline of order fulfillment
    3. To improve quality of products
    4. To increase facility utilization
    Select the correct answer using the code given below:

    A) 1, 2 and 4                     

    B) 2, 3 and 4

    C) 1, 2 and 3                     

    D) 1 and 3 only

    Correct Answer: A