List-I (Production Control Function) | List-II (Explanation) | ||
A. | Bill of Materials (BOM) | 1. | A technique for determining the quantity and timing of dependent demand items |
B. | Capacity Resource Planning (CRP) | 2. | A technique for determining personal and equipment capacities needed to meet the production objectives |
C. | Material Requirement Planning(MRP) | 3. | Specific what end items are to be |
D. | Master Production Schedule (MPS) | 4. | The part number and quantity required per assembly |
A) A\[\to \]4, B\[\to \]1, C\[\to \]2, D\[\to \]3
B) A\[\to \]3, B\[\to \]2, C\[\to \]1, D\[\to \]4
C) A\[\to \]4, B\[\to \]2, C\[\to \]1, D\[\to \]3
D) A\[\to \]3, B\[\to \]1, C\[\to \]2, D\[\to \]3
Correct Answer: C