Optimistic time \[{{t}_{0}}\] = 9 days pessimistic time \[{{t}_{p}}\] = 21 days and most likely time tg = days. |
The time approximates probability of completion of this activity in 13 days is: |
A) 16%
B) 34%
C) 50%
D) 84%
Correct Answer: A