    If 90 men can do a certain job in 16 days, working 12 h/day, then the part of that work which can be completed by 70 men in 24 days, working 8 h/day is [SSC CGL Tier II, 2015]

    A) \[\frac{7}{9}\]

    B) \[\frac{5}{8}\]

    C) \[\frac{1}{3}\]

    D) \[\frac{2}{3}\]

    Correct Answer: A

    Solution :

    [a] Let 70 men works 8h/ day and complete x part of that work in 24 days. Then, according to the question \[\frac{{{M}_{1}}\times {{H}_{1}}\times {{D}_{1}}}{{{W}_{1}}}=\frac{{{M}_{2}}\times {{H}_{2}}\times {{D}_{2}}}{{{W}_{2}}}\] \[\Rightarrow \]   \[\frac{90\times 12\times 16}{1}=\frac{70\times 8\times 24}{x}\] \[\Rightarrow \]   \[x=\frac{70\times 8\times 24}{90\times 12\times 16}\] \[\therefore \]      \[x=\frac{7}{9}\text{part}\]