SSC Quantitative Aptitude Time And Work Question Bank Work and Time (II)

  • question_answer
    A, B and C can do a job in 6 days, 12 days and 15 days respectively. After \[\frac{1}{8}\]of the work is completed, C leaves the job. Rest of the work is done by A and B together. Time taken to finish the work is             [SSC CGL Tier II, 2014]

    A) \[5\frac{5}{6}\text{days}\]

    B) \[5\frac{1}{4}\text{days}\]

    C) \[3\frac{1}{2}\text{days}\]

    D) \[3\frac{3}{4}\text{days}\]

    Correct Answer: C

    Solution :

    [c] As one day work\[=\frac{1}{6}\] B's one day work \[=\frac{1}{12}\] C's one day work\[=\frac{1}{15}\] Initially \[\frac{1}{8}\]of work was done So, the remaining work\[=1-\frac{1}{8}=\frac{7}{8}\] Now, \[\frac{7}{8}\]of the work is done by A and B (A and B)'s one day work             \[=\frac{1}{6}+\frac{1}{12}=\frac{2+1}{12}=\frac{13}{12}=\frac{1}{4}\] Let they together take x days to finish the work So,       \[\frac{1}{4}\times x=\frac{7}{8}\] \[x=\frac{7\times 4}{8}=\frac{7}{2}=3\frac{1}{2}\text{days}\]


You need to login to perform this action.
You will be redirected in 3 sec spinner