    A can do a work in 6 days and B in 9 days. How many days will both take together to complete the work?

    A)  7.5      

    B)  5.4

    C)  3.6

    D)  3

    Correct Answer: C

    Solution :

    According to question, A can finish the whole work in 6 days \[\therefore \] A's one day's work \[=\frac{1}{6}\] Similarly, 5's one day's work \[=\frac{1}{9}\](A + B)'s one day's work \[=\left( \frac{1}{6}+\frac{1}{9} \right)=\left( \frac{3+2}{18} \right)=\frac{5}{18}\] Therefore, (A + B)'s can finish the whole work in\[=\frac{18}{5}\]day i.e., 3.6 days