A) 70 days
B) 30 days
C) 40 days
D) 50 days
Correct Answer: C
Solution :
Let B does the whole work in x days. \[\therefore \]Work done by B in 1 day \[=\frac{1}{x}\] According to question, A does the\[\frac{1}{2}\]work in \[\frac{x}{6}\]days A does the whole work in \[\frac{2x}{6}\] days \[=\frac{x}{3}\] days \[\therefore \]Work done by A in one day \[=\frac{3}{x}\] \[\therefore \]Work done by A and B together in one day \[=\frac{1}{x}+\frac{3}{x}=\frac{4}{x}\] \[\therefore \]Time taken to complete the whole work by A and B together \[=\frac{1}{4}=\frac{x}{4}\] days Again, given that \[\frac{x}{\frac{4}{x}}=10\] \[x=40\]daysYou need to login to perform this action.