  • question_answer
    8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?    

    A)                        2

    B)  3           

    C)  4

    D)  5      

    Correct Answer: C

    Solution :

    Work done by 8 men In 6 days \[=\frac{6}{12}=\frac{1}{2}\] Remaining work \[=1-\frac{1}{2}=\frac{1}{2}\] 4 more men are engaged \[\therefore \]Total number of men \[=8+4=12\] By work and time formula \[\frac{{{W}_{1}}}{{{M}_{1}}{{D}_{1}}}=\frac{{{W}_{2}}}{{{M}_{2}}{{D}_{2}}},\]we have \[\frac{1}{8\times 12}=\frac{1}{\frac{2}{12\times {{D}_{2}}}}\] \[{{D}_{2}}=\frac{1}{2}\times \frac{8\times 12}{12}=4\]days