    Two men alone or three women alone can complete a piece of work in 4 days. In how many days can one woman and one man together complete the same piece of work?

    A) 6 days

    B) \[\frac{24}{5}\,\text{days}\]

    C) \[\frac{12}{1.75}\,\text{days}\]

    D) Cannot be determined

    E) None of the above

    Correct Answer: B

    Solution :

    \[2M=3W\]
    \[\therefore \] \[1M=\frac{3}{2}W\]
    Now, \[1M+1W=\frac{3}{2}W+1W=\frac{5}{2}W\]
    Number of days \[=\frac{3\times 4}{\frac{5}{2}}=\frac{24}{5}\text{days}\]