A and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and C can do the same in 12 days. Time taker by A, B and C together to do the job is |
A) 9 days
B) 8 days
C) 4 days
D) 5 days
Correct Answer: B
Solution :
\[(A+B)'s\]one day work \[=\frac{1}{15}\] |
\[(B+C)'s\] one day work \[=\frac{1}{10}\] |
\[(A+C)'s\] one day work \[=\frac{1}{12}\] |
\[\therefore \] \[2\,(A+B+C)=\frac{1}{15}+\frac{1}{10}+\frac{1}{12}\] |
\[\Rightarrow \] \[2\,(A+B+C)=\frac{4+6+5}{60}=\frac{15}{60}\] |
\[\Rightarrow \] \[2\,(A+B+C)=\frac{1}{4}\] |
\[\Rightarrow \] \[A+B+C=\frac{1}{8}\] |
\[\therefore \] A, B and C together will finish the work in 8 days. |