    A can do \[\frac{5}{8}th\] part of a work in. 15 days. Remaining work is done by B in 12 days. Then in how many days will A and B do same work by working together?

    A) \[11\frac{5}{7}\,\,days\]            

    B) \[12\frac{5}{7}\,\,days\]

    C) \[13\frac{5}{7}\,\,days\]

    D) \[14\frac{5}{7}\,\,days\]

    Correct Answer: C

    Solution :

    Time taken by A to complete \[\frac{5}{8}th\] part of a work =15 days
    \[\therefore \] One day work of \[A=\frac{1}{15}\times \frac{5}{8}=\frac{1}{24}\]
    Time takes by B to complete \[\frac{3}{8}th\] of work = 12 days.
    \[\therefore \] One day work of \[B=\frac{3}{8}\times \frac{1}{12}=\frac{1}{32}\]
    Together A and B one day work \[=\frac{1}{24}+\frac{1}{32}\]
                                        \[=\frac{4+3}{96}=\frac{7}{96}\]
    Hence, they will take \[\frac{96}{7}=13\frac{5}{7}\,\,days\] to complete the work together.