Banking Quantitative Aptitude Sample Paper Quantitative Aptitude Sample Paper-1

  • question_answer
    A can do a piece of work in 12 days and B in 15 days. They work together for 5 days and then B left. The days taken by A to finish the remaining work is                                                                         [NICL (AO) 2015]

    A)  3 days

    B)  5 days

    C)  10 days

    D)  12 days

    E)  15 days

    Correct Answer: A

    Solution :

    [a] Time taken by A and B both to complete the work \[=\,\,\frac{12\times 15}{27}=\frac{20}{3}\,\,days\]
    \[\therefore \]In 1 day, they can complete \[=\frac{3}{20}part\]
    \[\therefore \]In 5 day, then can complete \[=5\times \frac{3}{20}=\frac{3}{4}\,\,part\]
    Remaining work \[=\,\,1-\frac{3}{4}=\frac{1}{4}\]
    Time taken by A to complete the work \[=\,\,\frac{\frac{1}{4}}{\frac{1}{12}}=3\,\,days\]