    4 men can do a piece of work in 10 days, 2 women can do it in 15 days and 5 children can do it in 12 days. In how many days can 8 men, 5 women and 15 children together complete the piece of work (in days)?

    A) \[\frac{60}{37}\]           

    B) \[\frac{60}{47}\]

    C) \[\frac{60}{27}\]                                   

    D) \[\frac{60}{57}\]

    Correct Answer: A

    Solution :

    4 men's 1 day's work \[=\frac{1}{10}\]
    1 man's 1 day's work \[=\frac{1}{40}\]
    2 women's 1 day's work \[=\frac{1}{15}\]
    1 women's 1 day's works \[=\frac{1}{30}\]
    5 children 1 day's work \[=\frac{1}{12}\]
    1 child's 1 day's work \[=\frac{1}{60}\]
    (8 men + 6 women + 15 children)'s 1 day's works \[=\frac{8}{40}+\frac{5}{30}+\frac{15}{60}=\frac{1}{5}+\frac{1}{6}+\frac{1}{4}=\frac{37}{60}\]
    They finish the work in\[\frac{60}{37}\]days.