A certain number of men complete a piece of work in 40 days. If there were 8 men more the work could be finished in 10 days less. How many men were there afterwards? |
A) 27
B) 24
C) 18
D) 32
Correct Answer: D
Solution :
Let the number of men be x. So, x men can do a work in 40 days. \[(x+8)\] men can do the same work in \[(40-10)=30\,\,\text{days}\] |
According to the question, |
\[\therefore \] \[x\times 40=30\,\,(x+8)\] |
\[\Rightarrow \] \[40x=30x+240\]\[\Rightarrow \]\[x=24\] |
The number of men afterwards \[=24+8=32\,\,\text{men}\] |