    Working 7 h daily 24 men can complete a piece of work in 27 days. In how many days would 14 men complete the same piece of work working 9 h daily?

    A) 29                                

    B) 39   

    C) 36        

    D) 80

    Correct Answer: C

    Solution :

    Total work done by 24 men in 27 days with 7 h daily \[=24\times 7\times 27\]
    \[\therefore \]Required days \[=\frac{24\times 7\times 27}{9\times 14}=36\]