Banking Quantitative Aptitude Sample Paper Quantitative Aptitude Sample Paper-37

  • question_answer
    Two workers A and B working together complete the job in 5 days. If A worked twice as efficiently as he actually did and B worked 1/3 as efficiently as he actually did, the work would have been completed in 3 days. To complete the job alone, A would require                                                                              [SSC (CGL) 2013]

    A) \[5\frac{1}{2}\text{days}\]                    

    B) \[6\frac{1}{4}\text{days}\]

    C) (c)\[7\frac{1}{2}\text{days}\]                 

    D) \[8\frac{3}{4}\text{days}\]

    Correct Answer: B

    Solution :

    Let A and B complete the job in x and y days, respectively.
    Then,    \[\frac{1}{x}+\frac{1}{y}=\frac{1}{5}\]                        … (i)
    After changing efficiencies, A would be able to completed the work in \[\frac{x}{2}\]days and B in 3y days.
                \[\therefore \]      \[\frac{2}{x}+\frac{1}{3y}=\frac{1}{3}\]                                   … (ii)
    Solving Eqs. (i) and (ii), we get \[x=\frac{25}{4}=6\frac{1}{4}\text{days}\]


You need to login to perform this action.
You will be redirected in 3 sec spinner