    2 men can complete a piece of work in 6 days. 2 women can complete the same piece of work in 9 days, whereas 3 children can complete the same piece of work in 8 days. 3 women and 4 children worked together for 1 day. If only men were to finish the remaining work in 1 day, how many total men would be required?

    A) 4

    B) 8

    C) 6

    D) Cannot be determined

    E) None of the above

    Correct Answer: B

    Solution :

    1 man's one day work \[=\frac{1}{12}\]
    1 woman's one day work \[=\frac{1}{18}\]
    1 child's one day work \[=\frac{1}{24}\]
     1 man can finish the work in 12 days
    1 woman can finish the work in 18 days
    1 child can finish the work in 24 days
    \[\Rightarrow \] 12 men \[\equiv \] 18 women \[\equiv \] 24 children
    \[\Rightarrow \] 2 men \[\equiv \] 3 women \[\equiv \] 4 children
    Now, 3 women + 4 children = 4 men
     Part of work done by 4 men in 1 day \[=\frac{4}{12}=\frac{1}{3}\]
    Remaining work \[=1-\frac{1}{3}=\frac{2}{3}\]
     Remaining \[\frac{2}{3}\]work will be finished by 1 man in
                \[\frac{2}{3}\times 12=8\,days\]
      To finish the work In 1 day we require 8 more men.