    A work can be completed by P and Q in 12 days, Q and R in 15 days, R and P in 20 days. In how many days P alone can finish the work?

    A) 10                                

    B) 20

    C) 30        

    D) 60

    Correct Answer: C

    Solution :

    \[(P+Q)'s\]1 day's work \[=\frac{1}{12}\]              ....(i)
    \[(Q+R)'s\]1 day's work \[=\frac{1}{15}\]              ....(ii)
    \[(R+P)'s\]1 day's work  \[=\frac{1}{20}\]             ....(iii)
    On adding Eqs. (i), (ii) and (iii), we get
    \[2(P+Q+R)'s\]1 day's work
    \[=\frac{1}{12}+\frac{1}{15}+\frac{1}{20}=\frac{5+4+3}{60}=\frac{12}{60}=\frac{1}{5}\]
    \[\therefore \] \[(P+Q+R)'s\]1 day's work \[=\frac{1}{10}\]  ....(iv)
    \[\therefore \] P's 1 day s work \[=\,\,\frac{1}{10}-\frac{1}{15}=\frac{3-2}{30}=\frac{1}{30}\]
    So, P alone will complete the work in 30 days.