A) \[\frac{9}{40}\]
B) \[\frac{7}{40}\]
C) \[\frac{5}{40}\]
D) None of these
Correct Answer: A
Solution :
B's 1 day's work \[=\frac{1}{10}+\frac{1}{16}=\frac{13}{80}\] Now, (A + B)'s 1 day's work\[=\frac{1}{16}+\frac{13}{80}=\frac{18}{80}=\frac{9}{40}\] [B works for half day only] So, A and B together will complete the work in \[\frac{9}{40}\]days.You need to login to perform this action.