    P, Q and R can do a piece of work in 24 days, 30 days and 40 days, respectively. They start the work together but R leaves 4 days before the completion of the work. In how many days is the work done?

    A)  15                   

    B)  14

    C)  13                   

    D)  11

    Correct Answer: D

    Solution :

    Work done in x days, then \[\frac{x}{24}+\frac{x}{30}+\frac{x-4}{40}=1\] \[\Rightarrow \]   \[\frac{5x+4x+3x-12}{120}=1\] \[\Rightarrow \,\] \[12x-12=120\] \[\Rightarrow \,\]             \[12x=132\] \[\therefore \,\]                \[x\,=\,11\]