A) 5 days
B) 6 days
C) 8 days
D) 4 days
Correct Answer: C
Solution :
Work will complete in = K days \[\because \] \[14\,:\,12\,:\,:\,K\,:\,12\] \[16:28\] \[\therefore \] \[\,K=\frac{12\times 14\times 16}{12\times 28}=8\]daysYou need to login to perform this action.