A) \[10\frac{1}{3}\,\text{days}\]
B) \[12\frac{2}{3}\,\text{days}\]
C) \[13\frac{1}{3}\,\text{days}\]
D) \[8\frac{1}{4}\,\text{days}\]
Correct Answer: C
Solution :
Trick Remaining work \[=\frac{1-7}{10}=\frac{3}{10}\] part \[\because \] (A + B) take 4 days to do \[\frac{3}{10}\] of work. \[\therefore \] (A + B) will do the work in \[4\times \frac{10}{3}\text{days}\] \[=\frac{40}{3}=13\frac{1}{3}\text{days}\]You need to login to perform this action.