    If 6 men can do a piece of work in 30 days of 9 hours each, how many men will it take to do 10 times the amount of work if they work 25 days of 8 hours each ?

    A)  81 men

    B)  80 men

    C)  79 men

    D)  82 men

    Correct Answer: A

    Solution :

    [a] Number of man \[=\frac{30\times 6\times 9}{25\times 8}\times 10\] = 81 men