AFMC AFMC Solved Paper-2007

  • question_answer
    A and B can finisha piece of work in16 days while A alone can do the same work in 24 day sin how many days can B alone complete the work ?

    A)  56 days                                               

    B)  48 days

    C)   36 days                                              

    D)  164 days

    Correct Answer: B

    Solution :

                     Let B alone can complete the work = x days \[\therefore \](A + B)'s 1 day work\[=\frac{1}{24}+\frac{1}{x}=\frac{1}{16}\] \[\Rightarrow \,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\frac{1}{x}=\frac{1}{16}-\frac{1}{24}=\frac{1}{48}\]                 Hence, B alone completes the work in 48 days.