    16 men can complete a piece of work in 8 days. In how many days can 12 men complete the same piece of work?

    A)  10                   

    B)  \[9\frac{1}{3}\]

    C)  \[10\frac{2}{3}\]                

    D)  Cannot be determined

    Correct Answer: D

    Solution :

    16 men can do a work in = 8 days 1 man can do a work in \[=8\times 16\]days 12 men can do a work in \[=\frac{8\times 16}{12}\] days \[=10\frac{2}{3}\]days